Installation Steps for Electric Heating Thermal Oil Heaters

The installation steps can be divided into main phases: preparation, equipment installation, piping connection, electrical connection, commissioning, and inspection. Here are the detailed steps:

1. Preparation

Thorough preparation is essential before starting installation. This ensures smooth progress and reduces risks.

1.1. Equipment Acceptance & Inspection

  • Inspect the heater upon delivery.
  • Check for any transport damage.
  • Verify all accessories are present (heating elements, temperature controls, pump, electrical parts).
  • Confirm specifications match requirements (model, rated power, voltage, current).

1.2. Equipment Storage

  • Store the approved heater in a dry, ventilated area.
  • Protect it from moisture and contamination.
  • Keep electrical components especially dry.

1.3. Site Preparation

  • Choose a level, solid foundation.
  • Ensure no ground settlement or movement risk.
  • Provide sufficient space for installation, maintenance, and operation.
  • Keep the area free from flammable materials.
  • Prevent water accumulation.

2. Equipment Installation

2.1. Foundation Work

  • Prepare a suitable concrete foundation.
  • Base it on the equipment weight and dimensions.
  • Follow the design for foundation height.
  • Allow concrete to cure fully (usually 48+ hours).

2.2. Placing the Equipment

  • Position the heater on the foundation.
  • Ensure it is stable and level.
  • Use a spirit level to check.
  • Adjust with shims if needed.

2.3. Securing the Equipment

  • Fix the heater to the foundation securely.
  • Use expansion bolts or suitable fasteners.
  • Prevent any movement.
Installation

3. Piping Connection

3.1. Inlet/Outlet Piping

  • Connect to the thermal oil system according to drawings.
  • Ensure smooth pipe routing to/from heater ports.
  • Use suitable high-temperature pipe materials (e.g., stainless steel).
  • Ensure all connections are leak-tight (flanges, threaded).
  • Install pipe supports for long runs. Prevent sagging.

3.2. Installing the Oil Circulation Pump

  • Install the pump correctly. It is vital for oil flow.
  • Ensure pump ports align smoothly with pipes.
  • Prevent air ingress into the pump.
  • Use flexible connectors at pump connections. Absorb thermal expansion stress.
  • Check pump rotation direction is correct.
  • Use proper seals.

3.3. Installing Safety & Vent Valves

  • Install a safety valve. Prevent system overpressure.
  • Install vent valves. Remove air from the system.

4. Electrical Connection

4.1. Power Supply Connection

  • Connect to the correct three-phase power supply.
  • Ensure voltage and frequency match equipment specs.
  • Install suitable electrical switchgear. Include circuit breakers and overload protection.
  • Follow electrical safety codes. Avoid shorts or overloads.
  • Use appropriately sized cables. Match the rated power.

4.2. Control System Connection

  • Connect the control system wiring (temperature, level).
  • Ensure control power is connected correctly.
  • Verify all control components function.

4.3. Grounding (Earthing)

  • Connect a reliable equipment ground (earth).
  • This is critical for electrical safety.
  • It protects against electric shock and fire.

5. Commissioning & Inspection

5.1. Initial Checks

  • Check all pipe connections are tight. No leaks.
  • Verify all electrical connections are safe.
  • Test power supply and switches work.
  • Ensure temperature sensors and controllers are installed correctly.

5.2. Pre-Start Checks

  • Fill the system with clean thermal oil. Remove impurities.
  • Confirm the oil circulation pump runs normally.
  • Check control system settings match design.
  • Verify safety and vent valves function.

5.3. Start-up & Commissioning

  • Start the heater system.
  • Monitor parameters for stability. Look for abnormalities.
  • Observe oil temperature rise. Ensure heating works.
  • Gradually increase the load during testing.
  • Check system stability and safety.

5.4. Operational Checks

  • Verify temperature control stability.
  • Check oil circulation flow rate is normal.
  • Ensure oil distributes evenly.
  • Confirm safety devices work (over-temperature, over-pressure protection).

6. Summary

Installing an electric thermal oil heater https://8ruiyan.com/en/all-organic-heat-carrier-boilers/requires technical skill. Careful operation and thorough inspection are vital at every stage. Proper installation ensures safe and stable operation. Regular maintenance after installation is key for long-term reliability.

For further consultation, please contact our technical team for expert advice.

Whatsapp:86-19106101570

wechat:86-19106101570

email:nieyili@cnryan.com

http://www.8ruiyan.com

コメントを残す

メールアドレスが公開されることはありません。 が付いている欄は必須項目です